Reporting Schedule
Introduction
After completion of asset register worksheet, user could generate a simplify report which consist of
1.Movement of fixed asset
2.Disclosure information
Steps to create reporting schedule
1.Navigate to worksheet menu Asset plug-in> Worksheet and Schedule Property, Plant and equipment.
2.Left click menu "reporting".
3.Click on MFA button to generate asset movement table.
4.Select asset category position, then click Update grouping option button.
5.Click Generate movement button, and click Yes to confirm the generation,
6.Click Verify and Edit button to amend tabular figure.
7.Edit the amount (if applicable) and click Update button to save changes.
8.Click Refresh in the note button.
9.Click Auto-generate icon to generate disclosure as well.
10.The auto generated disclosure will be displayed below the MFA table.
|