Introduction

 

You may use table editor if want to present your data as following format.

 

 

 

Steps
 

1.Open your sub lead schedule (for example, circularisation of trade receivable)
 

2.Go to menu Process>Table editor
 

3.Select header : Fixed assets-cost/valuation


 

4.Key in Asset Category name at header column.
 

5.Enter the amount for each of the asset category, for opening balance and addition amount.
 

6.Select the line type: if you want to have all item sum up together, select "Total 1" as your line type.
 

7.Click Update and save to save the records.
 

8.Go to menu Process>Table editor again.
 

9.Select header : Fixed assets-accumulated depreciation


 

10.Enter the amount for each of the asset category, for opening depreciation and depreciation charges.
 

11.Click Update and save to save the records.

 

 

 

 